20. For external projects, who is responsible to provide the project statement of work?
A. Project manager
B. Sponsor
C. Customer
D. Project management team
20. 对于外部项目,谁负责提供项目工作说明书
A. 项目经理
B. 发起人
C. 客户
D. 项目管理团队
21.What is the LAST thing to do in project closure?
A. Complete the lessons learned
B. Provide the client with all pertinent documentation
C. Update the archives
D. Release the team
21. 在项目收尾时最后应该做的是:
A.完成经验总结
B.提供给客户所有相关的文档
C.更新档案
D.解散团队
22. Your customer asks for a small change in the project, which was not budgeted in the project. It is a small effort as compared to the total project and you need the goodwill of the customer for such a multimillion-dollar pipeline project. You will:
A. Refuse to do the work
B. Agree to do the work at no charge
C. Do the work and bill him later
D. Assess the cost and schedule impact and tell them you will decide later
22. 你的客户要求一个小的变更,它并没有包括在项目预算以内。和整个项目相比,这只是一个小的工作,而且对于这样一个几百万美元的管道项目,你需要客户的良好信赖。你应该:
A. 拒绝这一工作
B. 同意免费接受这一工作
C. 做这一工作,然后开票
D. 评估对进度和成本的影响,告诉他们,你随后再作决定
PMBOK指南(第5版)第三章习题(附答案)_IT认证_资格考试/认证_教育专区。PMBOK 指南(第5版)第三章习题(附答案) 1. Velidate scope is a (an) A. Planning...
PMBOK指南(第5版)第一章习题(附答案)_IT认证_资格考试/认证_教育专区。PMBOK 指南(第5版)第一章习题(附答案) 1.One of your team members informs you ...
PMBOK指南(第5版)第二章习题(附答案)_理学_高等教育_教育专区。PMBOK 指南(第5版)第二章习题(附答案) 1.You have been assigned as project manager on ...
PMBOK指南(第5版)第一章习题(附答案)_其它考试_资格考试/认证_教育专区。PMBOK指南(第5版)第一章习题(附答案)PMBOK 指南(第5版)第一章习题(附答案) 1....
PMBOK指南(第5版)第十一章习题(附答案)_从业资格考试_资格考试/认证_教育专区。PMBOK指南(第5版)第十一章习题(附答案)PMBOK 指南(第5版)第十一章习题(附...
PMBOK 指南(第5版)第二章习题(附答案) 1.You have been assigned as project manager on what could be a "bet the company" project. If the project is...
PMBOK指南(第5版)自测题390题(附答案详解)_从业资格考试_资格考试/认证_教育专区。PMBOK指南(第5版)自测题390题(附答案详解)heludd.taobao.com 友情整编 PMBOK...
PMP考试教材PMBOK指南第... 6页 7下载券 2012版项目管理过程组、... 5页...第 5 题: 正确答案:A 试题解答:参见 PMBOK 9.1.2.1 节。职责分配矩阵(...
PMBOK_2012_第五版__PMP_考前模拟题第2套 答案及解析_理学_高等教育_教育...参见:PMBOK 指南第 101 页。 考点与答题技巧:根据项目计划 考察项目范围的完成...
热门文档