PMBOK指南(第5版)第四章习题(附答案)

23. You are a member of a large government project. You know that the contract insists that all equipment be manufactured in the United States. You see a senior member of your team replacing a company etching on a piece of equipment that was made in a foreign country. You confront this person, and he says he is following the project manager’s orders. What should you do?

A. Nothing; the project manager made the decision.

B. Immediately report the violation to the government.

C. Update your resume and look for another job.

D. Talk to the project manager about the situation, and then decide what to do.

23. 你是一个大型政府项目的成员。你知道合同规定所有设备必须在美国生产。你看到团队中一个资深成员正在用国外生产的一件设备来替换锈蚀的配件。你面对这个人提出问题,他说他按照项目经理的指令做的,你应该:

A. 不做什么,项目经理做的决策。

B. 立即向政府报告。

C. 更新你的简历找新的工作。

D. 和项目经理交流这个情况,再作决定。

24.During project closure a project sponsor complains that the project did not increase the department’s knowledge of Java programming and therefore, the project is not complete. The customer has accepted the project. The project manager determines that all stated objectives and deliverables have been met. He does not find evidence that Java programming was an objective. A review of project correspondence shows no mention of the deliverable. The project manager should:

A. begin project closure.

B. re-plan the project to include the new objective.

C. meet with the team to discuss the issue and find a resolution.

D. get the project stakeholders involved to help resolve the issue.

24. 在一个项目收尾阶段,投资人抱怨该项目没有提升部门的Java 编程知识,因此该项目没有完成,但客户已经接受该项目。项目经理确定所有的规定目标和可交付成果均符合要求,没发现把Java 程序设计列为项目目标,回顾项目的相关信件表明没有提到过这一事项,项目经理应该:

A.开始项目收尾

B.重新规划项目以包含新的目标

C.召开团队会议讨论问题并寻求解决方案

D.通过相关项目干系人解决问题