PMBOK指南(第5版)第四章习题(附答案)

17.All of the following are characteristics of the project charter EXCEPT:

A. It is the document that formally authorizes a project.

B. It is issued by a project initiator or sponsor external to the project organization, at a level that is appropriate to funding the project.

C. It is used primarily to request bids for different phases of a project.

D. It provides the project manager with the authority to apply organizational resources to project activities.

17. 下列哪项不是项目章程的特点?

A. 一个正式批准一个项目的文档

B. 由项目组织以外的项目发起人或出资人发布,其层次根据项目需要

C. 用来在项目不同的阶段请求标书

D. 给项目经理提供权利应用组织资源到项目活动中

18. The requirement to complete the project in three months using only four resources is an example of:

A. constraints.

B. earned value analysis components.

C. benefit cost ratios.

D. law of diminishing returns.

18. 项目要求在三个月内完成,而只投入4个资源,这是一个什么情况的例子?

A.制约因素

B.实现值分析组成

C.收益成本比率

D.收益递减法则

19.Your company just a major new project. It will begin in three months and is valued at US $2 000 000.You are the project manager for an existing project. What is the FIRST thing you should do once you hear of the new project?

A. Ask management how the new project will use resources.

B. Resource level your project.

C. Crash your project.

D. Ask management how the new project will affect your project.

19.你们公司刚刚赢得一个大的新项目.项目将于三个月后开始,价值达2百万美元.你是目前执行的一个项目的项目经理.你在听到这个新项目的时候,应该做的第一件事情是什么?

A.询问管理层新项目将如何使用资源.

B.确定你自己的项目的资源水平.

C.进行项目赶工.

D.询问管理层,新项目对你的项目将产生何种影响.