WI-8710-8100-0099 Rev.B 汽机油系统设备及管道安装作业指导书

程中注意调整起吊绳索的平衡,避免设备与建筑物碰撞。

To lift LO station on the foundation by a pair of φ32.5 wire ropes 22m long through remained space. Sling balance shall be taken care to avoid collides. 吊装过程中,当设备下降到距基础约0.5m时穿上所有地脚螺栓拧上螺帽且露出螺帽

2~3扣,地脚螺栓的丝扣部分应涂黑铅粉,以利于以后松紧螺栓。然后将润滑油站吊放在已布置好的垫铁上,检查地脚螺栓与其孔壁四周应有间隙,其地脚螺栓末端不碰孔底。

When equipment lowering to 0.5 m above foundation, to fit all bolts and nuts and 2-3 threads to be left out, and black lead powder to applied to the treads for future loosing and tightening of bolts. Then to lay down on packs. To check for space between bolt and its hole.

采用斜铁调整润滑油站组件标高,组件与垫铁、垫铁与垫铁之间,0.05mm塞尺一般

应塞不进,局部塞入部分不得大于边长的1/4,其塞入深度不得超过侧边长的1/4,并且用0.3~0.5kg的手锤轻敲不动。

To apply slope packs to adjust equipment elevation, generally 0.05mm feeler cannot fill into in between component and packs or between packs.

然后利用千斤顶等工具,调整润滑油站使其纵横中心线误差小于10mm, 标高偏差

应在+10mm以内。

To adjust station by jacks and make deviation of centerline less than 10mm, and that of deviation within +10mm.

标高及纵横中心线找正都满足设计要求,经有关质检人员验收合格后,将油站底座

与垫铁、垫铁与垫铁之间用电焊点焊,每块垫铁不少于2点,再进行一、二次灌浆,灌浆前将地脚螺栓调正,使地脚螺栓位于螺栓孔的中间且螺栓下部不与螺栓孔壁接触;待灌浆料凝固达到设计强度的70%以上时紧固地脚螺栓,复查润滑油站组件标高及中心线仍符合要求,然后进行第二次灌浆。

Alignment of elevation and centerline shall comply with design requirement. After inspection and acceptance, to tack weld packs and base and carry out first or second grouting. Bolts alignment shall be done before grouting to make bolt in the center of the hole and lower part

WI-8710-8100-0099, Rev.B page 9 of 19

上一页第9页

你可能喜欢

  • 汽轮机检修
  • 背压式汽轮机
  • 汽轮机轴承
  • 汽轮机发电
  • 施工现场安全管理制度
  • 汽轮机安装
  • 管道安装施工方案

热门文档

相关文档

站点地图 | 文档上传 | 侵权投诉 | 手机版
本站所有资源均来自互联网,本站只负责收集和整理,均不承担任何法律责任,如有侵权等其它行为请联系我们.
文档下载 Copyright 2013 doc.guandang.net All Rights Reserved.  -  email