冷镀锌化合物
4.4.1 Organic cold galvanizing compound shall be used to field repair damaged galvanized surfaces.
Materials and repairs shall be according to ASTM A 780. The following products are approved for use. 现场修理被损坏的镀锌表面时必须使用有机冷镀锌化合物。材料和修理都必须符合ASTM A 780的
标准。准许使用以下产品:
4.4.1.1 Galvanox Type 1 as manufactured by the Subox Division of the Carboline Company, St. Louis,
MO, Phone (314) 644-1000.
由密苏里州炭化物公司Subox分公司生产的Galvanox Type 1牌产品。(电话 (314) 644-1000)。
4.4.1.2 ZRC Cold Galvanizing Compound as manufactured by ZRC Worldwide, Marshfield, MA, Phone
(781) 319-0400.
由马里兰州ZRC Worldwide 国际公司制造的ZRC牌冷镀锌化合物。(电话(781) 319-0400)。
4.4.2 Surfaces to be repaired shall be clean, dry, and free of oil, grease, and corrosion products. If the area
to be repaired includes welds, first remove all flux residue and weld spatter by mechanical means (e.g., chipping). Areas shall be power disc sanded to bright metal. To ensure that a smooth coating can be effected, surface preparation shall extend into the undamaged galvanized coating. The paint shall be spray or brush applied in multiple coats until a dry film thickness of 8 mils minimum has been achieved. 需要修理的表面必须干净、干燥并且没有油、油脂和腐蚀产物。如果需要修理处有焊缝,首先用机械手段(例如錾)去除所有的焊渣和焊药残留物。这些区域必须进行电动喷沙清理,使金属表面露出光亮的金属本色。为了确保涂层光滑平整,表面准备必须延伸到镀锌涂层未受损坏的位置。必须采用喷或涂的方式修补涂刷,要涂上多层,直到形成最低厚度为8 mils的干膜为止。
4.4.3 A finish coat of aluminum paint shall be applied to provide a color blend with the surrounding
galvanizing. Coating thickness shall be verified by measurement with a magnetic or electromagnetic gauge.
铝涂层上的最后一层涂料必须与周围的镀锌颜色协调。必须用磁性仪表或电磁仪表进行测量,确
认涂层厚度。
5.1 ERECTION安装
5.1 General
一般要求
5.1.1 Erection shall include unloading, storage, inventory control, removing from storage, hauling to the
place of erection, and erecting all structural and miscellaneous steel at the project site.
安装工作必须包括在项目现场卸载、储存、库存控制、从仓库移出、运往安装地点和安装所有的
钢结构和多金属结构件。
5.1.2 The work shall comply with the provisions of Chapter M, Section M4, "Erection" of the AISC
"Specification for Structural Steel Buildings" and with Section 7, "Erection" of the "Code of
Standard Practice for Steel Buildings and Bridges."
安装工作必须符合AISC“钢结构建筑物标准” 的“安装”部分第M章第M4节和“钢建筑物和桥
梁的标准实施办法”的“安装”部分第 7节的要求。
5.1.3 Moderate amounts of reaming, chipping, welding, or cutting for correction of errors is permitted.
Methods of correction of errors shall have the prior written approval of the Air Products
representative.
为了修正错误,进行适度的铰、錾、焊接或切割是允许的。修正错误的方法必须事先经 APCI 代
表的批准。
5.1.4 Throughout the period of structural steel erection, members shall be adequately braced and
guyed to resist wind and other loads that might be imposed on the incomplete structure.
在整个钢结构安装期间,结构件必须加以充分的支撑和加固以抵御风力和其它负载对尚未安装好
的结构的影响。
钢结构安装施工方案_建筑/土木_工程科技_专业资料。钢结构安装施工方案BSCC 上海宝钢工程建设总公司 联合车间吊装施工技术方案 吊装施工技术方案 1.工程概况 1.工程概...
钢结构安装要求_建筑/土木_工程科技_专业资料。钢结构安装要求钢结构的安装要求: (1)本工程的技术要求系钢结构制作并安装完毕后的最终要求, 不包括工艺余量及加工...
钢结构安装施工方案_建筑/土木_工程科技_专业资料。非常实用大为制氨有限公司 50 万吨年产合成氨项目煤气化装置钢结构 钢结构安装施工方案 1 工程概述 1.1 大为...
17.1 17.1.1 (1) 钢结构制作安装方案 工程概述 由于本工程的详细设计没有完成,根据我公司对此类工程的经验,本工程 钢结构主要是管架钢结构、工艺结构用钢...
钢结构安装施工方案_建筑/土木_工程科技_专业资料 暂无评价0人阅读0次下载举报文档 钢结构安装施工方案_建筑/土木_工程科技_专业资料。钢结构施工的组织设计...
钢结构安装记录_建筑/土木_工程科技_专业资料。SH3503J211 钢结构安装记录位 号 检查 点数 5 5 5 5 5 5 5 5 5 5 工程名称:30 万吨/年乙烯法 VCM 扩建项...
钢结构厂房安装协议依据《合同法》及相关法律、法规之规定,经甲乙双方自愿达成如下共识; 甲方: 乙方: 一、工程概述, 工程地址: 工程名称: 工程面积:约; 工程工...
钢构件安装施工方案 1 工艺流程 1.1.焊接操作工艺流程 焊接安全设施的准备、检查 安装材料 坡口检查 坡口检查记录 气象条件的记录 坡口表面的清理 局部预热 定位...
安装施工方案 中国化学工程第七建设有限公司 漳州腾龙芳烃(PX)项目部 4 漳州古蕾海腾码头投资管理有限公司 罐区管廊安装工程第Ⅱ标段(31~64 段) 钢结构制作安装...
钢结构吊装及安装施工方案_建筑/土木_工程科技_专业资料。【钢结构吊装及安装施工方案】 第一章 1.1、 钢结构设计图纸。 编制依据 1.2、《钢结构工程施工质量验...
热门文档