1. Mrs. Lucky won’t like being charged more for one job when the same number

and type of announcements were produced in each job.

2. May: Actual rate = $20,000/500 = $40 per hour Overhead assigned: $40 5 = $200

June and July: Actual rate = $20,000/250 = $80 per hour Overhead assigned: $80 5 = $400

3. Predetermined rate = $240,000/(500 12) = $40 per hour

Cost and price of each job: Direct materials Direct labor

Overhead (5 $40) Total cost

Plus 25% markup Price

$250.00 25.00 $475.00

Using a predetermined rate will avoid the nonuniform production problem re-vealed in the first two requirements and result in a more accurate application of overhead and fairer costing of the summer jobs.