43. You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. Which document provides this information?

A. Resource assignment matrix

B. Change control system

C. Project charter

D. Client organization chart

43.在一个项目的实施过程中,你接管这个项目。你需要了解谁有权力批准范围的修订,从哪个文件中可以获得这一信息?

A. 资源分配矩阵

B.变更控制系统

C.项目章程

D.客户组织关系图

44. An oil field development project manager believes that modifying the project scope may increase production and will increase the owner’s profit level. What should the project manager do?

A. Change the WBS

B. Contact the customer to improve understanding

C. Call a meeting with the project team

D. Update the scope management plan

44. 一个油田开发项目的经理认为修改项目范围可以增加产量并提高业主的利润率,他应该:

A. 变更WBS

B. 联系客户、加强了解

C. 召集项目团队会议

D. 更新项目管理计划

45.Your approved cost baseline has changed because of a major scope change on your project. Your next step should be to

A. Estimate the magnitude of the scope change

B. Issue a budget update

C. Document lessons learned

D. Execute the approved scope change

45. 你项目的一项较大的范围变更改变了经你核准通过的成本基线。下一步你应该怎么做

A. 评估范围变更的幅度

B. 发布更新的预算

C. 制作学到的经验教训的说明文件