PMBOK指南(第5版)第四章习题(附答案)

B.管理层

C.项目团队

D.职能经理

40. The project sponsor decided to interrupt funding for your project. You should?

A. Stop work immediately and release all resources.

B. Decrease team size

C. Start closing the project.

D. Remove non-critical tasks.

40. 项目发起人决定中断你的项目的资金,你应该?

A. 马上停止工作,并释放所有资源

B. 缩小团队规模

C. 开始项目收尾 D. 删除非关键任务

41. A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a

result of this change?

A. Inform the customer

B. Make sure marketing is aware of the change. C. Understand what functionality was added.

D. Implement change control processes to track the change.

41. 一位团队成员在对项目增加额外功能后,才向你汇报:该额外增加的功能对项目成本或进度计划没有影响。针对这种变更,应该如何做?

A. 通知客户.

B. 确保营销部门了解变更一事.

C. 了解增了什么功能.

D. 执行变更控制过程对变更进行跟踪

42.What is the function of CCB?

A. approving and rejecting the requested changes

B. Specification and Standard Change

C. Project Performance Review

D. Determination of the Management Reserve

42. 变更控制委员会(CCB)的职能是什么?

A.批准或否决变更请求

B.规范与标准变更

C.项目绩效审查