In this paper, a virtual factory is proposed in the form of a distributed simulation model which provides a tool for performance evaluation of large and complex manufacturing systems. The virtual factory is constructed on a computer network developed for c
in the MRP system. Minor planning activities, such asrescheduling, will also be done whenever necessary.The structural features of a factory and the require-ments for a factory-wide simulation system are mostlysatisfied by a distributed simulation system when it isdeveloped on a distributed computer system and in-stalled as part of the CIM system infrastructure. Eachsubsystem at the area level can be modeled on oneprocessor, and a transportation system connecting ar-eas is modeled on another processor. Functions forinformation exchange among areas are also necessaryto model the collection of data. One processor can alsobe allocated to modeling global decisions and collect-ing status reports of areas.
3.2Constructing Steps of Virtual Factory
To construct a virtual factory, we consider the follow-ing procedure:
Step 1—Areas and transportation systems are mod-eled independently on computers (or processors) assimulation models of subsystems, Area i(i = 1, 2...)and Transportation Processes, respectively. A Trans-portation Process may be abbreviated to T-Process inthe following. In this step, the material flow withineach subsystem is the primary focus of the model. Thearrival of material from other subsystems and the de-parture of material from the subsystem to other sub-systems are generally represented by the functions ofsource and sink nodes, respectively, in a simulationmodel as shown in Figure 3.
Step 2. Simulation models developed in Step 1 areconnected by a computer network to be integrated intoa total simulation model. In order to express the glo-bal material flow among subsystems, source and sinknodes in a simulation model of a subsystem are con-nected by specially designed messages transmittedthrough the computer network system to appropriatesink and source nodes of other models, as shown in

Figure 4. In reality, any transportation among areas is
Figure 2. A factory with areas connected

by a transportation system
effective in saving the effort of developing a total sim-ulation model. In this paper, we concentrate the dis-cussion on realizing the material flow or the physicaldistribution of products among subsystems. Otheraspects such as information exchange for decisionmaking, and the adjustments of statistics in the simu-lation are items for future research.
3.Structure of a Virtual Factory
3.1Shop Floor Activities
Figure 1 shows the shop floor activities and planningactivities. Areas in the figure could correspond toFMS’s, machine shops, and storage areas. The trans-portation system is a system connecting the areasshown in Figure 2 that transports work and productsfrom one area to the other. A global production planis periodically generated based on the status informa-tion collected from areas. Local plans are made basedon the global plan. The time interval for such periodicplanning activities may correspond to the Time Bucket
Figure 3. Simulation models of area and T-Process
MARCH 1999
SIMULATION3
system for job-shop manufacturing- A system ...Through the integration of these mechanisms into a...An improved genetic algorithm for the distributed ...
system for job-shop manufacturing- A system ...Through the integration of these mechanisms into a...An improved genetic algorithm for the distributed ...