WI-8710-8100-0099 Rev.B 汽机油系统设备及管道安装作业指导书

11.1 所有管段和管件在安装前用丙酮彻底清理,并用干燥压缩空气吹净。

All pipes and fittings shall be cleaned by acetone and cleared by dry compressed air.

11.2 所有管段落料、热工测点开孔均采用机械方式,严禁火焰切割。

All pipe cutting, boring of I/C system shall be done with machine, flare cutting prohibited.

11.3 所有焊接坡口均采用机械加工。

All grooves to be done by machine.

11.4 管道在安装前组织汽机和热工专业技术员和质检员认真进行工艺检查,与图纸查 对系统的正确性、完整性。

Technicians and inspectors shall carry out process check for system correctness

and integrality before piping installation.

11.5 管件清洗后封口放置于室内干燥通风处并及时组织力量施工,以免造成管道内部的再次腐蚀。

Cleaned and ends closed pipes shall be stored in dry and well-ventilated indoor area, and to be installed as soon as possible to avoid secondary inner corrosion. 11.6 管件在安装时,每一管件内部,每一管口对接都由专人检查,当天未完工作,敞开口的封堵和第二天拆封均由专人检查后方可安装。

11.7油系统管道的焊接均采用混合气体保护焊。

Oil piping shall be welded by mixed gas shield welding.

11.8 所有法兰垫片涂专用涂料,法兰紧固按法兰紧固工艺要求进行。

All flanges shall be applied with special coat, fastening of flanges shall be done as per requirement.

12. 对相关专业的要求requirement for related disciplines

12.1汽机房润滑油站基础正对的+17.950米及+11.950米层的平台及横梁暂缓施工,待润滑油站组件就位后再施工。

Ele.+17.950m and +11.950 platforms and beams shall be hold until positioning of LO station.

WI-8710-8100-0099, Rev.B page 17 of 19

上一页第17页

你可能喜欢

  • 汽轮机检修
  • 背压式汽轮机
  • 汽轮机轴承
  • 汽轮机发电
  • 施工现场安全管理制度
  • 汽轮机安装
  • 管道安装施工方案

热门文档

相关文档

站点地图 | 文档上传 | 侵权投诉 | 手机版
本站所有资源均来自互联网,本站只负责收集和整理,均不承担任何法律责任,如有侵权等其它行为请联系我们.
文档下载 Copyright 2013 doc.guandang.net All Rights Reserved.  -  email