Abstract Lessons Learned The Texas Experience

has been operated as a single control area for less than two years following an approximately two-year design phase. The market in ERCOT differs from the Federal Energy Regulatory Commission’s Standard Market Design (SMD) and from other electricity market

Lessons Learned: The Texas Experience

Ross Baldick and Hui Niu

The University of Texas at Austin

Abstract

The wholesale electricity market of the Electric Reliability Council of Texas (ERCOT) has been operated as a single control area for less than two years following an approximately two-year design phase. The market in ERCOT differs from the Federal Energy Regulatory Commission’s Standard Market Design (SMD) and from other electricity markets in many aspects. This paper presents a description of the ERCOT market and lessons that can be drawn from the Texas experience.

1. Introduction

Electricity market reform has taken place over the last 15 years in various countries. There are more than a dozen existing restructured electricity markets in the United States and around the world1. The markets vary in terms of the market organization, system operation, transmission charges, congestion management, and investment incentives. These differences are often related to the history of the particular system, asset ownership, operational practices, and philosophical perspectives. Some markets have a day-ahead market for spot trading while some others have just a day-ahead scheduling process together with a short-term market to facilitate real time operations.

Because of various difficulties and problems experienced, each market has changed in some aspects. Some markets have undertaken big changes, such as the California market and the