MPC - Batch production system planning and control

MPC-BASIC THEORY

Batch production system planning and control

Batch Production Planning and Control In general the planning of batch processing requires the solution of three problems:

1. Determination of batch sizes i.e. the quantity of items or customers to be processed at one time.

2. Batch sequencing, i.e. the determination of the order in which batches of different items or customers will be processed.

3. Batch scheduling, i.e. the timing of the processing of batches of items or customers. The critical problem in batch production is a question of control, i.e. that of ensuring that orders progress as planned. Batch production is often undertaken for a customer delivery promise, whereas mass production plans can be made because of fewer products and the use of specially designed equipment. Here, deviations from plans can mostly be caused by mechanical

breakdowns. With batch production, interaction between jobs is less certain, as is the completion time of each operation (since time is not standardised, variations in element times occur). Problems regarding batch production can occur for a multiplicity of reasons such as machine breakdown, quality problems (need for re-working), material movement (causing loss or

damage), operator performance (varies because of the manufacture of different batches), variable queuing time and tooling availability.

1. Batch quantities which are too large will result in high stock levels and cause a large amount of capital to be tied up in stock which might otherwise be invested elsewhere. Additionally, unduly high stock levels will incur other costs, such as the cost of stock-keeping, insurance, depreciation, etc. on the other hand, batch quantities which are too small will result in both low stock levels, which may be insufficient to meet large fluctuations in demand, and also the frequent processing of small batches, each time incurring costs associated with set-up, ordering etc.

The problem then is to determine the optimal batch size that minimises total costs; consequently we must consider the following:

a. Stock holding

b. Processing

c. Set-up and preparation of machines and equipment.

These are reflected in a formula which gives us the minimum cost batch size‘ (E.O.Q.) or (E.B.Q.).

EBQ = √ 2Cs R

第1页