1. 2.

Department 1 uses process costing. Department 2 uses job-order costing. Direct materials Direct labor

Applied overhead (100% of $250) Total cost

$ 500 250 5–8

1. Security rate = $50,000/$500,000 = 0.10 or 10% of materials cost Machining rate = $36,000/2,000 = $18 per MHr Other overhead rate = $74,000/$160,000 = 0.4625, or 46.25% of direct labor

cost

2. Direct materials $500 Direct labor 250 Applied overhead: Security (0.10 $500) 50 Machining ($18 2 MHrs.) 36 Other (0.4625 $250) Total cost

*Rounded

3. Dave already keeps track of direct labor hours (for the plantwide overhead

rate application) and of direct materials cost. The only additional driver is machine hours. These could be noted on the labor time ticket in a separate column, or a separate form for machine usage, perhaps located at each ma-chine, could be developed. The form would be similar to a labor time ticket, noting the date, time started and ended, and the job number.