1. Overhead applied in August: 2. 3. 4. 5.

Job #214: $1,800/$10 = 180 $16 = $2,880 Job #215: $4,000/$10 = 400 $16 = $6,400 Job #216: $150/$10 = 15 $16 = $240 Job #217: $800/$10 = 80 $16 = $1,280

Beginning balance Direct materials Direct labor

Applied overhead Total cost

$13,400 2,200 1,800 $ 9,670 9,000 4,000 $ 0 1,500 150 $ 0 3,450 800 Ending balance in Work in Process = Job #215 + Job #216 + Job #217 = $29,070 + $1,890 + $5,530 = $36,490 Cost of Goods Sold = Job #214 = $20,280

Price of Job #214 = $20,280 + (0.3)($20,280) = $26,364

LaSalle would only need a finished goods account if jobs were not imme-diately sold to customers. For example, if a shed were built on spec (specu-lating that it could be sold), or if a shed that was previously contracted for was unacceptable to the customer and the customer refused to buy it. In gen-eral, LaSalle would move finished jobs directly from work in process to cost of goods sold.