屋面工程施工方案(改)

中铁建设集团济南分公司文华园项目部

屋面工程施工方案(改)

历山路危房改造工程屋面工程施工方案

目 录

一、

编制依据 ························································································································ 2

施工图纸及施工组织设计····················································································· 2

1.1.

1.2. 标准、规范、规程及其他························································································· 2

二、 施工部位的工程概况···································································································· 2

2.1. 建筑与结构设计概况································································································· 2 2.2.施工特点、重点与难点······························································································· 4 三、 施工准备 ························································································································ 4

3.1.技术准备······················································································································· 4 3.2.材料及机具准备··········································································································· 4 四、 施工安排 ························································································································ 4

4.1 施工顺序安排··············································································································· 5 4.2人员、时间安排············································································································ 5 五、 主要施工方法及工艺···································································································· 6

5.1工艺流程 ························································································································ 6 5.2作业条件 ························································································································ 6 5.3防水层施工···················································································································· 6 5.4找坡层施工·················································································································· 10 5.5找平层施工···················································································································11 5.6保温层施工·················································································································· 13 5.7 种植屋面保护层施工································································································· 13 5.8过滤层施工·················································································································· 14 5.9屋面细部做法·············································································································· 16 六、 质量标准 ······················································································································ 22

6.1主控项目 ······················································································································ 22 6.2一般项目 ······················································································································ 22 6.3允许偏差项目·············································································································· 23 七、 成品保护 ······················································································································ 23 八、 安全、环保措施 ·········································································································· 24

8.1安全要求 ······················································································································ 24 8.2环保要求 ······················································································································ 24 九、 成本节约措施 ·············································································································· 25 十、 分包管理 ······················································································································ 25

第1页

上一页第2页

你可能喜欢

  • 装饰施工组织设计方案范本
  • 挂瓦坡屋面施工方案
  • 屋面挤塑聚苯板保温施工方案
  • SBS屋面防水施工方案
  • 钢筋工程施工方案
  • 屋面保温施工方案
  • 建筑节能专项施工方案
  • 屋面SBS改性沥青防水卷材施工

热门文档

相关文档

  • 屋面工程施工方案(改)

    《屋面防水工程施工及验收规范》 《砌体结构设计规范》 《建筑工程施工质量验收统一标准》 《屋面工程技术规范》 《高聚物改性沥青卷材屋面防水层施工工艺标准》 《...

  • 屋面工程施工方案(修改后)11.9

    《弹性体改性沥青防水卷材》 GB/T 19520-2003《聚氨酯防水涂料》 河南省标准图集 05YJ 系列 屋面工程施工方案 本工程施工设计图纸,图纸会审内容,设计变更单,甲方...

  • 屋面工程施工方案(改)

    屋面工程做法概况 北侧门厅为彩钢板保温屋面,由钢结构专业分包厂家加工制作安 装,具体做法及细部质量要求详见分包单位编制的钢结构屋面专项施工 方案,在此不再赘述。 ...

  • 屋面工程施工方案新

    《屋面工程技术规范》 《改性沥青卷材屋面防水层施工工艺标准》 编号 GB50207-2002 GBJ207-83 L01J202 GB50300-2001 GB50345-2004 GY1005-1996 注:施工过程中如...

  • 屋面防水工程施工组织设计方案(修改版)

    现行版本:B 修改码:0 中国延安干部学院学员宿舍楼屋面防水工程 施工方案 陕西省第三建筑工程公司 中国延安干部学院学员宿舍楼项目经理部 2004 年 3 月 30 日 ...

  • 屋面工程施工方案

    屋面工程施工方案 编制: 审核: 审批: 河北建设集团有限公司二〇一三年八月五日... 50 厚挤塑聚苯保温板 3mm+3mm 改性沥青防水卷材 楼顶屋面 (除楼 梯间、 ...

  • 屋面工程施工方案(新)

    刷高聚物改性沥青涂料一遍隔气层南通建筑工程总承包有限公司 第 1 页共 17 页 2008 年 4 月 临沂同心花园 1#、2#、3#楼 【屋面工程施工方案】 6.1: 8 ...

  • 屋面工程施工方案

    不上人屋面 屋面工程施工方案 6 北京万兴建筑集团 翻建书库项目 基层清理 加气...4.2.4. 自粘性 SBS 改性沥青卷材防水层施工(满铺法) (1)在基层清理后,...

  • 屋面平改坡工程施工方案

    屋面平改坡工程施工方案_建筑/土木_工程科技_专业资料 暂无评价0人阅读0次下载举报文档 屋面平改坡工程施工方案_建筑/土木_工程科技_专业资料。2013 年大兴区...

  • 屋面工程施工方案

    13 0 建安工程————屋面工程施工方案 中兴通讯工业园南区二期人才公寓 1 栋...设计修改补充、洽商 1.6、屋面工程质量验收规范 GB50207-2002 1.7、建筑构造...