泥浆护壁钻孔灌注桩在施工工艺过程中质量控制及通病防治

泥浆护壁钻孔灌注桩在施工工艺过程中

质量控制及通病防治

【摘要】在桩基工程中采用泥浆护壁钻孔灌注桩(以下简称:钻孔灌注桩)施工工艺比较普遍,它是一种地下隐蔽工程,施工过程中极易出现质量问题。因此,就加强施工材料、施工工艺等质量控制来有效的防治通病的发生及相关的处理措施作一综合探讨。

【关键词】钻孔灌注桩;施工工艺;质量控制;通病防治;处理措施

Quality control and common problems prevention of slurry Wall Construction of bored piles in process

Chen Jie, Zhu Yi, Mo Ying-hui

(Nuclear Industry Nanjing Construction Group Co., Ltd.NanjingJiangsu210003)

【Abstract】Foundation works in the use of bored piles in Slurry Wall (hereinafter referred to as: bored piles) CoMParison of the construction process in general, it is a hidden underground works, the construction process are vulnerable to quality problems occur. Therefore, on the strengthening of the construction materials, construction techniques, such as quality control to effectively control the occurrence of common and related measures for a comprehensive deal to explore.【Key words】Bored pile; Construction technology; Quality control; Common problems prevention; Treatment measures

1. 概述钻孔灌注桩具有无噪音、无震动、无积压等优点。适用于地下水位以下的黏性土、粉土、砂土、填土、碎(砾)石土及风化岩层。但其施工过程部位无法直接观察,属地下隐蔽工程,成桩后也不能进行开挖验收,在施工中极易发生质量通病,若防止不妥,将直接影响到整个工程的质量和进度,甚至给投资者造成巨大的经济损失和不良的社会影响。

2. 成桩工序钻孔灌注桩成孔、成桩工序是:定桩位→护筒埋设→钻机就位→钻孔→终孔→第一次清孔→下放钢筋笼→接入导管→第二次清孔→灌注混凝土。在工程开工时宜做试桩,提供设计参数。

3. 质量控制

3.1施工前的审查

施工前对施工单位各项审查,是有效的控制手段。一般要进行资质审查、施工组织设计审查、组织设计交底及图纸会审、审查是否根据地质资料可能在钻孔灌注桩施工中发生的问题加以分析,并制定出相应的质量保证及处理措施、还要审查成桩机械的鉴定合格证件是否有效、控制点复核记录等工作。由于钻孔灌注桩施工的隐蔽性及工序的不可逆转性,要求基础施工队伍认真落实实施施工组织设计方案,并加强施工质量管理,密切抓好施工过程中每一个环节的质量,力争将隐患消除在成桩之前。

3.2对相关人员的岗前教育。开工前要对相关人员进行上岗前教育,成桩质量是此工程的重要基础,做到人人重视质量。开工后要不定时检查操作人员,班报表记录员、质检人员的在岗情况,特别是质检人员的在岗情况及钻进记录情况,监理人员要及时做好工序的检测验收。

3.3对原材料的检验。为确保成桩质量,设专职质量检查员,负责施工过程中的质量