PMBOK指南(第5版)第四章习题(附答案)

7.While the project is being completed, management requests a change. What is the FIRST thing the project manager should do?

A. Comply with the request if possible

B. Obtain a complete understanding of the scope of the change

C. Tell the customer that a change will be coming

D. Ask the team to accept the change

7. 项目完成的时候,管理层要求进行个变更,项目经理首先应该做什么?

A. 如果可能完成这个要求

B. 对范围的变更获得完全的理解

C. 告诉客户变更即将发生

D. 要求团队接受此变更

8.Procurement closeout is different with close project in the procurement closeout:

A. Occurs before close project

B. Is the only one to involve the customer

C. Includes the return of the project

D. May be done more that once for each contract

8. 采购收尾不同于项目收尾,在于采购收尾是:

A. 发生在项目收尾前

B. 是唯一有客户参与的阶段

C. 包含归还财产

D. 可能在一个合同过程中进行多次

9. All of the following are correct statements about a project manager except?

A. They are assigned after work performance reports are distributed

B. They have the authority to say no when necessary

C. They manage changes and factors that create change

D. They are held accountable for project success or failure

9. 下列都是关于项目经理的正确描述,除了:

A. 他们在工作绩效报告分发之后被指派到项目中

B.他们有在必要时说不的权力

C.他们管理变更以及产生变更的因素

D. 他们对项目的成功或失败负责

10. Project manager is involved in the development of the project charter.He needs to further develop project justification.Which of the following is the best idea?

A. Interview with the sponsor

B. Collect organizational process assets,especially focus on historical information

上一页第3页