分包商合同终止会议-会议纪要-英文版

由于分包商执行合同不力,严重迟缓了项目进度,因此总包商、分包商和监理在现场召开会议决定终止分包合同。

The Project Manager Of the Sub-Contractor, Mr. XXXputs forward the list of Status On Site according to the requirements of the Consultants and states that they have completed all the under processing works on the site and rectified all the defects that have been remarked during the inspection of last Site Meeting.

c. Main Contractor:

The Project Manager Of The Main Contractor, Mr. XXX points out that there still exist some defects in the works of the Sub-Contractor after hearing about the statements of Mr. XXX. For example, there is one check point (K139+900) less 5cm than the specification for the Top Embankment and there still exist some weeds on the road surface from K124+000 to K129+000 ect. However, the Main Contractor still can accept the works that have been handed over to him.

B. The Works From K141+000 To K145+000

a. Consultant:

The Deputy R.E. of the Consultant, Mr. XXX states that though the Sub-Contractor has completed the works for the Clearing and Grubbing, Stripping and NGL Compaction for the section from K141+000 to K145+000 before, all the area has grown up lots of grasses again. Therefore, all the works that have been done should be repeated again. However, the Main Contractor still could give some allowance for the works that have been done by the Sub-Contractor.

b. Main Contractor:

After some consulting with the Consultant and the Sub-Contractor, the Main Contractor finally agrees with that all the works done in the section from K141+000 to K145+000 should be paid by 50% of itsOriginal Quantities, including the Clearing & Grubbing, Stripping and NGL Compaction.

C. Service Road From K141+000 To K143+000

a. Sub-Contractor:

The Project Manager Of the Sub-Contractor, Mr. xxx states that the Sub-Contractor has constructed the Service Road from K141+000 to K143+000 additionally and requested some compensation from the Main Contractor.

b. Main Contractor:

The Main Contractor refuses the request of the Sub-Contractor and states

上一页第2页

热门文档

相关文档

  • 会议纪要

    会议纪要_工作总结/汇报_总结/汇报_应用文书。...要提交分包商合同的执行计划给 YHHI, 供应商的计划...制作结束之后提交给 YHHI B 所有文件以英文呈现 C ...

  • 会议纪要范例

    (九)AFC: (1)本周工作进展:①样机验收;②分包商合同的签订。 (2)下周工作...7.业主意见: (一)要求监理提交监理周报,完成相关会议的会议纪要; (二)图纸...

  • 纪〔2013〕 号 关于“集团对分包商管理”的会议纪要

    “集团对分包商管理”的会议纪要时间:2013 年 4 月 26 日 13:00-14:40 地点:董事长办公室 会议议题:集团对分包商管理 主持:汪成夫 记录:唐良强 参会人员:...

  • 培训会议纪要

    培训会议纪要_演讲/主持_工作范文_实用文档。培训会议纪要会议时间: 会议地点:...文件接收和分包合同签署;总承包商代表(项目经理); 误期违约金;工程预付款的...

  • 培训会议纪要

    培训会议纪要_演讲/主持_工作范文_应用文书。培训会议纪要会议时间:2014 年 11...文件接收和分包合同签署;总承包商代表(项目经理); 误期违约金;工程预付款的...

  • 项目合约管理

    组织有关合同评审(分包)的会议,没有会议纪要的扣 ... 分包招标文件、 合同评审及前期的分包商推荐报告/... 不按照规定的程序及时办理合同变更、解除、终止等...

  • 工程公司会议纪要模板

    扬州安装工程公司 会议时间:2001 年 7 月 23 日 会议地点: 会议纪要: 1....以上记录的会议纪要将作为机电分包合同的一部分, 请分包商予以确 认(签字盖章)...

  • 《中铁二院分包商管理》

    项目会有更多的补充协议。 7、分包商授权度更高,...整改期限结束,检查人员应对其进行复查,直到复查 合格...会议结束后会形成一份会议纪要,在 48 小时内送至...

  • 工程公司会议纪要模板

    投标分包商名称:扬州安装工程公司 会议时间:2001 ...以上记录的会议纪要将作为机电分包合同的一部分, 请... 英文个人简历模板 创意简历模板汇集 推理型题分析与...

  • s-w-m--会议纪要(20131219)

    安委会会议纪要 时间:2013 年 12 月 19 日 10:...7、CD 座及地下车库的电消检合同已签订,尚未进行...加强对园区服务分包商管理; 7、做好相关能源供应工作...

站点地图 | 文档上传 | 侵权投诉 | 手机版
本站所有资源均来自互联网,本站只负责收集和整理,均不承担任何法律责任,如有侵权等其它行为请联系我们.
文档下载 Copyright 2013 doc.guandang.net All Rights Reserved.  -  email